    • Voltmeter
          Voltmeter is used to indicate the voltage of the generator and that of the utility supply
      Casing
          This is the structure which enclose the main construction of the automatic change-over panel. It is constructed using metal sheet of thickness 2mm. the shape of the change-over panel is first drawn on a plane paper with dimension that will adequately accommodate the change-over panel.
          The required dimension is then traced out on the iron sheet chisel and hammers where used to cut the traced end.
          After this, each part are joined together by the use of welding machine and the necessary holes for both and screw where drilled on the change-over house required.
          After the construction, this change-over panel is then painted. The tools used for the construction are:-
          Chisel
          Hammer
          File
          Welding machine
      4.5.1     Testing, maintenance and discussion
           Testing is an important process in the engineering field especially in both electrical and electronics engineering.
          Therefore, testing can be define as the process by which any faulty condition is detected before a dangerous situation arose.
          Having designed and construction or installed s system with an appropriate selected materials component and equipment what now remain is to put the system into use.
      However, before the system is put use, it must be tasted and inspected to ensure that is complies with regulation of installation.
      Below is the test carried out.
          Polarity test
          Insulation resistance test between the alive and neutral conductors
          Insulation resistance test between earth and non-earthling conductors
          Earthling test
      4.5.2     POLARITY TEST
          This test is carried out on the construction of automatic change-over panel to ensure that only live conductor is taken through the beaker on the load contactor.
      4.5.3     INSULATION RESISTANCE TEST BETWEEN THE LIVE AND NEUTRAL CONDUCTORS
      An insulation resistance test was made between live and neutral conductor to ensure that there are no short-circuit in the wiring
      One lead from the insulation tester was connected to the outgoing live terminal and the other to the neutral of the main switch. The instrument is operated and accurate reading was reading out.
      4.5.4     EARTLING TEST
      This test carried out to ensure that there is no leakage to the body of appliance.
          On led of ohm meter is placed on conductor and the other lead to the body of appliance. Zero resistance indicates that there is no leakage to the body.
      4.6     MAINTENANCE OF CONTACTOR AND IINSTALLATION
          Generally the contact and wiring of the contactor should be properly maintained for adequate functioning of the contactors. In addition, the following should be a also be put into consideration. To replace an operating coil, the contactor must be removed from enclosure and the following procedure must be under taken.
      (i)    Remove the spring-clip on either side of the contactor, carefully live the auxiliary contact compress coil magnet slight and take whole magnet system and moving contact carries from auxiliary contact button
      (ii)    Invert the assembly and lift out the lift magnet and coil vertically, taken care that the magnet spring remain in place. Note the position of the coil terminations.
      (iii)    Change the coil and re-assemble the unity by reversing the above procedure, remembering to compress slightly the magnet when replacing the auxiliary contact.

  • CHAPTER FOUR -- [Total Page(s) 4]

    Page 4 of 4

    Previous   1 2 3 4
    • ABSRACT - [ Total Page(s): 1 ]ABSTRACT    The main aim of any electric power supply in the world is to provide uninterrupted power supply at all times to all its consumers. Although in developing countries, the electric power generated to meet the demands of the growing consumers of electricity is insufficient hence instability and outage.    Power instability or outage in general does not promote development in the public and private sector. The inventors do not feel secure to come into a country with constant or freq ... Continue reading---

         

      APPENDIX A - [ Total Page(s): 1 ]BILL OF ENGENEERING MEARSUREMENT AND EVALUTION (BEME)The table below shows the cost estimate in naira and kobo of constructed automatic change-over panel.Bill of Engineering Measurement and Evaluation ... Continue reading---

         

      TABLE OF CONTENTS - [ Total Page(s): 1 ]TABLE OF CONTENTS Title Page   Certification   Acknowledgements  Abstract   Table of Contents   CHAPTER ONE1.1    Introduction  1.2    Aim and Objective of the Project  1.3    Scope of the Project CHAPTER TWO2.1    Literature Review  2.2    Manual Change-over Switch  2.3    Automatic Change-over Switch  2.4    Related Work 2.5    Reasons for Automatic Change-over Switch  2.6    Problems of Automatic Change-over Switch  CHAPTER THREE3.1    Methodolog ... Continue reading---

         

      CHAPTER ONE - [ Total Page(s): 1 ]CHAPTER ONE1.1    INTRODUCTION     Power instability in developing countries creates a need for automation of electrical power generation or alternative sources of power to back-up the utility supply. This automation is requiring as the rate of power outages become predominantly high. Research in the field of electrical electronics engineering has led to the tremendous discovers and inventions especially in the area of automation and power control. These invention have been useful in solvi ... Continue reading---

         

      CHAPTER TWO - [ Total Page(s): 4 ]The circuit diagram of the flip flop and switching transistor stage of the related art.Another related art was the development of a single phase automatic change-over switch. This also related to the present invention i.e. it switches electrical power supply from public supply to generator in the event of a power outage or insufficient voltage but it is apply to single phase system while the present invention is apply to three (3) phase system, moreover, the system uses an electronic control cir ... Continue reading---

         

      CHAPTER THREE - [ Total Page(s): 4 ]START AND STOP BUTTONS     These two push buttons are used to close and open the circuit respectively. The start push button is a normally open type (NO) while the stop push button is a normally close (NO) type to breaker the circuit when need arise3.5     CONTACTOR    Is a device designed for repeatedly making and breaking an electronic power circuit. It is usually operated magnetically. It can be operated in line or be remotely governed by pilot devices or relay. And when there is a s ... Continue reading---

         

      CHAPTER FIVE - [ Total Page(s): 1 ]CHAPTER FIVE5.1     CONCLUSION    The automatic change-over switch has immense advantage in every area where power is required it is a fact that there is hardly any aspect of human life were electrical power is not required, at home, offices, hospital, etc.    It find a wide application scope, wherever the re-ability of electrical supply is necessary, for switching to an alternative source from main.5.2     RECOMMENDATIONThe automatic change-over switch is needed in every home and of ... Continue reading---

         

      REFRENCES - [ Total Page(s): 1 ]REFERENCEB.L. and A.K. Theraja (1997): Electrical Technology, S. chand company LTDEngr. A.O Aduloju (2003): Electrical Power System, Evidence Nigeria VentureEngr. M.B Jenyo (2007): Electrical Power System III & IV lecture Notes, UnpublishedEngr. T.A. Mustapha (2006): Electrical Power System I & II inn lecture Notes, unpublishedInternet Research: http://www.electricalsolution.comM.S. Ahmed, A.S. Mohammed & C.B. Augusibo (2006): Development of a single Automatic change-over switch Federal Universi ... Continue reading---